Mulch: Bulk vs. Bag Math and How to Quote It
Bulk is almost always cheaper per cubic yard, but only if you can receive a load, stage it and move it efficiently. The math below lets you decide per job.
Core conversions
1 cubic yard = 27 cubic feet Cubic yards = bed sq ft x depth in inches / 12 / 27 (= sq ft x inches / 324) 2 cu ft bags per yard = 27 / 2 = 13.5
Bag sizes vary by product. Read the label and substitute the real volume.
Worked example
A 1,200 sq ft bed at 3 inches deep with 5% waste: 1,200 x 3 / 324 x 1.05 = 11.67 cubic yards, or about 158 two-cubic-foot bags (157.5).
Compare cost per yard
Bagged cost per yard = price per bag x 13.5 Bulk cost per yard = (price per yard x yards + delivery) / yards
Example prices for illustration only: a $4.50 bag costs $60.75 per yard; bulk at $38 per yard with a $75 delivery fee on 11.67 yards costs $44.43 per yard. Use your supplier's current prices.
Build the bid in this order
- Material and delivery at your cost.
- Labor: yards x install man-hours per yard x burdened rate. Time it on your own jobs; wheelbarrow distance changes everything.
- Markup on material and delivery, because you carry the buying risk.
- Check net margin on the whole bid.
Run it in the Mulch, Topsoil & Gravel Bid Calculator. Same math works for topsoil and gravel; check the weight limit of your truck for stone.