Labor Burden Breakdown: What One Man-Hour Really Costs
A field tech paid $20 an hour does not cost you $20 an hour. Four layers sit on top of the wage, and skipping any of them is how a full schedule still ends the year with no profit.
The four layers
- Payroll burden. Employer payroll taxes and any benefits, as a percentage of wages. Use your payroll provider's actual numbers.
- Workers' comp. Charged as a rate on payroll by class code. Read your policy; do not guess.
- Non-billable time. Drive time, loading, fueling, shop time and weather standby are paid but not invoiced.
- Overhead. Trucks, trailers, mowers, insurance, fuel, software and phones, spread over billable hours.
Worked example (illustrative inputs)
Wage $20, payroll tax 10%, workers' comp 8%, non-billable 25%, annual overhead $38,000, 3 techs, 1,500 billable hours each, 15% target net margin.
Burdened wage = 20 x (1 + 0.10 + 0.08) = $23.60 per paid hour Labor per billable = 23.60 / (1 - 0.25) = $31.47 Overhead per hour = 38,000 / (1,500 x 3) = $8.44 Break-even rate = 31.47 + 8.44 = $39.91 per man-hour Target rate = 39.91 / (1 - 0.15) = $46.95 per man-hour
The target divides by (1 - margin) because margin is a share of the price. Multiplying by 1.15 would deliver only about 13% net.
What to do with the number
Use the target rate as the labor line in every bid. Then check your current prices: any job that returns less than the break-even rate per man-hour loses money before you pay yourself.
Try your own inputs in the Man-Hour Rate Calculator, or use the workbook version with a crew roster.